Abu Qir power station The process of restoring the outputs of units 1-5
Establishing a temporary barrier (gates) and completely drying the water inside the facility.
Breaking and removing all concrete covering of all walls of the structure above and below the water level and the external sides of the structure.
Replacing all worn-out iron with new iron and planting chemabox markers to stabilize the new iron and restoring the concrete cover in accordance with For engineering specifications and measurements.
Year: 3122 Work location: Abu Qir Power Station Subject of the contract: Restoration of the water outlet of units 5 – 2 Duration of contract implementation: 4 months Client name: West Delta Electricity Production Company